Anyone that has done lots of double layer ceilings could you please explain the etiquitte of the first layer. I'm hanging in a building with only a couple (load bearing) interior walls. On my first layer I was breaking all my butts on the same joist. Their is going to be a wall built under this joist after we get ceiling drywalled. Contractor says shouldn't you stagger those butts I said as long as none of my joints (seams or butts) of the second layer break the same as the first layer that should be good. What are your thoughts on that.
Normally I would just hang as usual and just stagger my second layer with first but contractor wants me to hang out so far with second layer so they can start framing behind me.
Normally I would just hang as usual and just stagger my second layer with first but contractor wants me to hang out so far with second layer so they can start framing behind me.