Just hung and taped 3 sheets of 5/8" for behind a commercial grille and the inspector decided he wanted hat channel and another layer of 5/8" added.
My question is, how the hell do you install hat channel? I've never had to learn!
Would I install it perpendicular to the studs on 16" centers? Do you screw both sides of the hat?
Any help would be great! Thanks!
Also, what is a good price to charge to install it? (Labor)