Estimating taping and finishing compond
we run automatic taping tools
iam have trouble estimating the taping and finishing compond on my jobs dose any one know a good idea how much tape i need say per 1000 square foot and taping compond i need say per 1000 square foot and how much finishing compond i need say per 1000 square foot |
|
|
|
|
|
#2 |
|
Senior Member
Trade: Builder
Join Date: May 2008
Location: Western New York
Posts: 262
Thanks: 1
Thanked 64 Times in 38 Posts
|
Re: Estimating taping and finishing compond
Best idea is to keep track of what you use on all your individual jobs. After a while, a good average will appear. That's what we did years ago.
|
|
|
|
|
|
#3 |
|
Super Moderator
Trade: Drywall Contractor / Hanger
Join Date: Dec 2008
Location: KCMO area
Posts: 904
Thanks: 0
Thanked 35 Times in 23 Posts
|
Re: Estimating taping and finishing compond
drywalltalk.com/f2/mudd-calculation-783
here's an entire thread devoted to the topic.
__________________
www.partnersconstruction-drywall.com |
|
|
|
|
|
#4 |
|
The Drywall King!
Trade: Drywall Contractor - Frame-Finish
Join Date: Jun 2008
Location: Miami, FL
Posts: 649
Thanks: 25
Thanked 46 Times in 32 Posts
|
Re: Estimating taping and finishing compond
when you become a professional at finishing and reached your peak, you will eyeball the job and figure out how many buckets of mud and tape you need. You then will only end up with a half of bucket left over, for touchups.
|
|
|
|
|
|
#5 |
|
I hang the board
Trade: drywall boarder
Join Date: Jan 2010
Location: Cranbrook
Posts: 16
Thanks: 0
Thanked 2 Times in 2 Posts
|
Re: Estimating taping and finishing compond
well thanks for your guys pointless replys if you dont know why would you post crap in my thread some where out there was a forumula for this i just lost it but joepro if your such a pro you should have a better idea then me how to do it if you dont know what iam asking stay out of my thread joepro the drywall king lol get real man
|
|
|
|
|
|
#6 |
|
Super Moderator
Trade: Drywall Contractor / Hanger
Join Date: Dec 2008
Location: KCMO area
Posts: 904
Thanks: 0
Thanked 35 Times in 23 Posts
|
Re: Estimating taping and finishing compond
Burns, chill out. If you'd bother too look at the thread I posted for you, you'd see that we all figure it a bit different. Something like "how much mud do I need?" is a question none of us even really think about. We learned that kind of thing long ago and never give it much thought. In fact, I seldom ever figure it myself, my supply house knows my multiplier and, based on the footage of my order, send it out. I have it figured so I almost always have just 1 or 2 boxes left, better than to be short. I pick up the extra when I check over the work and collect.
__________________
www.partnersconstruction-drywall.com |
|
|
|
|
|
#7 | |
|
Senior Member
Trade: Drywall
Join Date: Dec 2009
Location: NC
Posts: 2,012
Thanks: 755
Thanked 672 Times in 422 Posts
|
Re: Estimating taping and finishing compondQuote:
|
|
|
|
|
| The Following User Says Thank You to Capt-sheetrock For This Useful Post: | gotmud (09-12-2011) |
|
|
#8 |
|
Junior Member
Trade: drywall finisher
Join Date: Dec 2009
Location: alaska
Posts: 21
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Estimating taping and finishing compond
bush your looking at 1 roll of tape,1 or 2 boxes of taping and 3 boxes of topping to start..then you can go from there..its only about 20 sheets with 12's
|
|
|
|
|
|
#9 |
|
Junior Member
Trade: drywall finisher
Join Date: Dec 2009
Location: alaska
Posts: 21
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Estimating taping and finishing compond
sorry its burns..lol
|
|
|
|
|
|
#10 |
|
I hang the board
Trade: drywall boarder
Join Date: Jan 2010
Location: Cranbrook
Posts: 16
Thanks: 0
Thanked 2 Times in 2 Posts
|
Re: Estimating taping and finishing compond |
|
|
|
|
|
#11 | |
|
Super Moderator
Trade: Drywall Contractor
Join Date: Oct 2008
Location: Northern MN
Posts: 951
Thanks: 9
Thanked 134 Times in 73 Posts
|
Re: Estimating taping and finishing compondQuote:
__________________
aka the rock doctor |
|
|
|
|
|
|
#12 |
|
Junior Member
Trade: Metal Stud & Drywall Estimator
Join Date: Sep 2011
Location: Riverside County
Posts: 2
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Estimating taping and finishing compond
Estimating Commercial Drywall - Taping Mud Level 4
Per 1000/SF (1/2) Roll of Tape (Typ Waste Factor 25%) (1) 49lb Box of All Purpose (Typ Waste Factor 6%) (3) 49lb Box of Topping (Typ Waste Factor 8%) Estimating Housing Drywall - Taping Mud Level 3 (1) Roll of Tape (Typ Waste Factor 10%) (1) 49lb Box of All Purpose (Typ Waste Factor 8%) (2) 49lb Box of Topping (Typ Waste Factor 8%) |
|
|
|
|
|
#13 |
|
Senior Member
Trade: W&C Contractor
Join Date: Feb 2011
Location: Boganville, Australia
Posts: 268
Thanks: 3
Thanked 53 Times in 43 Posts
|
Re: Estimating taping and finishing compond |
|
|
|
|
|
#14 |
|
Junior Member
Trade: Metal Stud & Drywall Estimator
Join Date: Sep 2011
Location: Riverside County
Posts: 2
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Estimating taping and finishing compond
Hi Jason,
Yes, Commercial drywall we stand up our drywall. Example: 100/LF of wall 10' Ht. = 1000/SF You will have a tape joint every 4/LF @ 10' HT. 100/LF / 4 = 25 25 X 10' Ht. = 250/LF of tape The 25% waste takes care of corner bead and whats dropped on the ground. We have our guys tape corner bead up from the ground 4' so as trades drag there cords around on the job, they don't rip the corner bead off the wall and the added tape on the corner bead does the trick. |
|
|
|
|
|
#15 | |
|
FASTER THAN A MARE
Trade: Taper
Join Date: Dec 2010
Location: New York
Posts: 517
Thanks: 99
Thanked 79 Times in 71 Posts
|
Re: Estimating taping and finishing compondQuote:
Well I thought about it and thought apla-tech can't touch this guy for spotting nails he makes no run back to the mud pail I bet he beads fast with his no waste Apla-Pants technique Last edited by Bazooka-Joe; 09-12-2011 at 08:03 PM. |
|
|
|
|
![]() |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Construction cost estimating book ?? | d-rock | General Drywall Discussion | 4 | 06-20-2011 03:58 PM |
| Estimating Methods/strategies | d-rock | General Drywall Discussion | 21 | 01-18-2010 08:43 AM |
| Estimating software | d-rock | Business, Marketing, and Sales | 13 | 01-17-2010 10:51 AM |
| Bidding / Estimating Process | silverstilts | General Drywall Discussion | 31 | 07-02-2009 12:15 AM |
| Taping & finishing an offset joint | Ace | Drywall Finishing | 9 | 04-18-2009 03:30 AM |
| Go to Page... |