I'm curious as to what production levels other finishers are accomplishing. I don't wish to talk income or pricing here, simply production levels such as how much footage per foot you are reaching and if you are using hand tools ony or you are using mechanical tools.
Personally, I'm using hand tools and reach about 180 square feet per hour on my finishing time. I have reached as high as 200 feet per hour but can reach 180 on average. I would be interested to know what other finishers are accomplishing. This would be on a finished job, 3 coats. Doesn't matter what materials you use or how you accomplish it. Just curious as to what production levels you are achieving.
__________________
WallmasterDrywall.com |
|
|
|
|
|
#2 |
|
Member
Trade: Drywall-Plaster Contractor
Join Date: Jul 2008
Posts: 75
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Production Levels
12- 15000 feet a week with 2 man crew stomp texture maybe another day if smooth lids. these are not easy homes, lots of detail.
|
|
|
|
|
|
#3 |
|
Member
Trade: taping and spackling
Join Date: Mar 2009
Posts: 88
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Production Levels
300-500 boards per 6 days if all goes well..3 coats ready to paint!!
|
|
|
|
|
|
#4 |
|
Senior Member
Trade: Residential & Commercial Drywall, Doublewides, Remodeling
Join Date: Jan 2009
Location: Sierra Vista, AZ
Posts: 397
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production Levels
Can you guys specify whether this is the norm in your area. Some crews are wicked fast, I just like to know averages to make sure my own guys are at least up to par.
|
|
|
|
|
|
#5 |
|
Super Moderator
Trade: Drywall Contractor / Hanger
Join Date: Dec 2008
Location: KCMO area
Posts: 904
Thanks: 0
Thanked 35 Times in 23 Posts
|
Re: Production Levels
Pretty close to 10k per week per man. With tools, ready to spray. If close (job to job) maybe more.
|
|
|
|
|
|
#6 | |
|
What's a Mudder to do?
Trade: Drywall Finisher
Join Date: Sep 2008
Location: Earth
Posts: 72
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production LevelsQuote:
From what I've been told about what other finishers like me are earning in a week, the footage per hour breaks down to around 6000 square feet per week which isn't very fast in my opinion, it's a comfortable pace however. I would say that an experienced finisher should be producing about 7300 square feet per week if he is working full time. The faster people will be turning out 8,000 to 10,000 square feet per week. That's also considering that they are turning out high quality work.
__________________
WallmasterDrywall.com |
|
|
|
|
|
|
#7 |
|
What's a Mudder to do?
Trade: Drywall Finisher
Join Date: Sep 2008
Location: Earth
Posts: 72
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production Levels
I would like to know what some of you think is faster, hand tools or mechanical or pneumatic tools? I invested $5400 in Apla-Tech tools and I can finish with hand tools almost as fast. The Apla-tech tools also had high maintenance costs compared to hand tools. I would like to hear other thoughts on this as well and what your experience has been with various tools.
__________________
WallmasterDrywall.com |
|
|
|
|
|
#8 |
|
Senior Member
Trade: drywaller/taper/texturer
Join Date: Apr 2008
Location: brandon manitoba canada
Posts: 222
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Production Levels
i have never tried the apla-tec sytem by itself but combined it with graco (cfs) just looking at the system gives me a headache those coaters that are supposed to replace yur boxes look like a make work idea because they probably need to be followed by a knife for good results.The maintenance on the mark5 justify it's productiveness, jmo though.
|
|
|
|
|
|
#9 |
|
Senior Member
Trade: Residential & Commercial Drywall, Doublewides, Remodeling
Join Date: Jan 2009
Location: Sierra Vista, AZ
Posts: 397
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production Levels
I don't have apla tech, but when I do it will be in tandem with my columbia boxes.
|
|
|
|
|
|
#10 |
|
Senior Member
Trade: drywaller/taper/texturer
Join Date: Apr 2008
Location: brandon manitoba canada
Posts: 222
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Production Levels
drilled holes through my old columbia boxes and modified them for apla/graco system,could not bring myself to harming my tape tech ones
|
|
|
|
|
|
#11 |
|
Junior Member
Trade: finisher
Join Date: Mar 2009
Posts: 2
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Production Levels
id like to know what some of these houses look like. on average it takes me and two other guys 35 hours to finish an average 12000 foot house with 9' ceilings. typically two bedrooms have vaulted ceilings and usually a large great room with some scaffold work. usually 40 sheets or so to finish from a scaffold. this includes putting on an average of 80 peices of corner bead.
|
|
|
|
|
|
#12 |
|
Member
Trade: taping and spackling
Join Date: Mar 2009
Posts: 88
Thanks: 0
Thanked 0 Times in 0 Posts
|
Re: Production Levels
i think if you have the continuous flow boxes they are faster but the job needs to be big..
|
|
|
|
|
|
#13 | |
|
What's a Mudder to do?
Trade: Drywall Finisher
Join Date: Sep 2008
Location: Earth
Posts: 72
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production LevelsQuote:
That was my view on them also. I had a rather large house about 3 years ago and one man working for me, the upstairs alone was about 14,000 square feet of board. I ran the apla-tech tools and put on quite a bit of mud myself while he went and did the hand things. Trouble is that he was so slow that the high production I generated didn't put me ahead. He no longer works for me of course and my thought is that if I had a guy that was actually earning his keep the day would have been more productive. I had coated the entire upstairs myself that day and put on about buckets of compound. The next day I was doing a lot of hand work however where the flats meet the inside angles in order to flatten them. An earlier job I had done I did differently and with a kid that had some experience with finishing and with the apla-tech tools. It had about 10,000 square feet of board in this house and we put the tape on the inside angles and then second coated the flats in about 4.5 hours. I had him wipe the flat seams after I applied the compound with an arched drywall trowel. Why the trowel? It's faster than a knife on your second coat because in one pass you are tapering your edges and smothing the flat rather than 3 passes as you would have to with a knife. Incidentally the money I earned in that short time was equivalent to what I would have done in about 7 hours with hand tools. So in my experience you can make time with automation if you have someone working with you and knows what they are doing.
__________________
WallmasterDrywall.com Last edited by JoeMudder; 03-21-2009 at 12:01 PM. |
|
|
|
|
|
|
#14 | |
|
What's a Mudder to do?
Trade: Drywall Finisher
Join Date: Sep 2008
Location: Earth
Posts: 72
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production LevelsQuote:
__________________
WallmasterDrywall.com |
|
|
|
|
|
|
#15 |
|
What's a Mudder to do?
Trade: Drywall Finisher
Join Date: Sep 2008
Location: Earth
Posts: 72
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production Levels
Does your production average more than 200 square feet per hour with your tools?
__________________
WallmasterDrywall.com |
|
|
|
|
|
#16 | |
|
Senior Member
Trade: drywall and framing
Join Date: Sep 2008
Location: Tampa Bay
Posts: 142
Thanks: 8
Thanked 9 Times in 5 Posts
|
Re: Production LevelsQuote:
Are you using the cfs boxes? When we run our cfs boxes we don't wipe 3 passes with a knife behind it. We only tune up the corners were we start the box from, the lap marks, and around light cans or boxs a lil. We don't wipe over the whole joint with a knife. The boxes leave a nice finish. |
|
|
|
|
|
|
#17 | |
|
What's a Mudder to do?
Trade: Drywall Finisher
Join Date: Sep 2008
Location: Earth
Posts: 72
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production LevelsQuote:
I haven't tried their new taping system that resembles a bazooka, but it looks fast. I had purchased mine prior to them coming out with the taper, so when I taped with them I used a corner applicator to apply the compound, then layed the paper tape in by hand and then used a roll plow to wipe it out. My hand taping isn't too bad however. On 8,000 square feet of board I can usually tape all the inside corners and put the second coat on all the flats in a day just using hand tools. When I talked to the people at apla-tech to learn what production levels were being achieved, it wasn't much faster than what I can do by hand. And for the maintenance costs it wasn't worth it to me. I can coat my inside angles by hand as fast as their angle coater does it because of the fact that the angles require two coats when using the apla-tech angle coater. They will tell you that you can coat both sides of the angles in one minute or less with their coater, and it's true because I've done it. What they don't tell you of course is the time it takes to go back around and pick all the corners and the bottoms of those angles. I did a lot of time studies on production using various methods and it takes me about 3.5 hours using hand tools to coat one side of the angles on about 8,000 square feet of board with some extras. such as a couple cathedrals or 9' ceilings. You might save yourself one hour with the apla-tech tools coating angles, but you have to spend $300.00 for the coating head. It just isn't worth it to me for the production I can do with hand tools. Also, the angle head broke on me and for the repairs on it isn't worth replacing in my book. You can figure it out according to what you get per foot, but with hand tools my production level on average comes out to 193 square feet per hour. When I talked to the guy at apla-tech and we walked production levels according to what he has done with them, he told me that he did a 7,000 square foot job in two weekends. If he worked 8 hour days his production level was about 218 square feet per hour which isn't much higher than what I do with hand tools. And if he worked 10 hour days, that means I'm faster than the apla-tech tools which are also supposed to be faster than any of the mechanical tool systems.
__________________
WallmasterDrywall.com Last edited by JoeMudder; 03-23-2009 at 11:02 AM. |
|
|
|
|
|
|
#18 | |
|
Senior Member
Trade: drywall and framing
Join Date: Sep 2008
Location: Tampa Bay
Posts: 142
Thanks: 8
Thanked 9 Times in 5 Posts
|
Re: Production LevelsQuote:
I know about the alpa-techs, we are running them too, but we are running the cfs(continus flow system check out there website) with the slim line boxes, not the pneumatic system. We roll and glaze the angles when we tape them with the taping tube and then only have run them once with the 3" head. we only need to pick the corners, bottems and lap marks. they come out great for a light orange peel texture. my old man is super fast at runnin angles by hand (both sides at once) and the system smokes him by hand but you need to have two people doing it to make it worth it. If not you spend too much time switchen back and forth between the tools. |
|
|
|
|
|
|
#19 |
|
Senior Member
Trade: Residential & Commercial Drywall, Doublewides, Remodeling
Join Date: Jan 2009
Location: Sierra Vista, AZ
Posts: 397
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production Levels |
|
|
|
|
|
#20 | |
|
What's a Mudder to do?
Trade: Drywall Finisher
Join Date: Sep 2008
Location: Earth
Posts: 72
Thanks: 0
Thanked 1 Time in 1 Post
|
Re: Production LevelsQuote:
__________________
WallmasterDrywall.com |
|
|
|
|
![]() |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Taping with Tools Production | compute | Drywall Finishing | 19 | 04-27-2009 09:36 AM |
| Custom/Production Boarder | wire2008ca | Introductions | 0 | 01-11-2009 05:46 PM |
| Go to Page... |